Timelines

Planning approvals                                                            end March 2009 Completed

Sorting timber for building (Ben Law)                                    Feb/March Completed

Completion of fund raising                                                  end June Completed

Foundation (see UTube)                                                    4th July "A" frame Completed

Start of build proper                                                         July onwards Completed

Completion of building                                                       September Half way there

Finishings and fixtures                                                       October

Staff training                                                                  September

Shop opening                                                                  November 7th